RENOVATION OF THE SCHOOL IN BORODYANKA TOWN

Project value: 7 944 784,80 Eur

Estimated duration of project implementation: the aim is to open up school spaces for students by the end of autumn 2023 and by the end of 2023 to install a bomb shelter, and outdoor infrastructure.

The aim of the project: to rebuild and equip one of the three schools in the Borodyanka town of Kiev region. The school is designed for 700 children who study in grades 1-12.

CloseProject activities and status

1. Preparation of the Technical work project. Procurement of the Technical work project preparation was finished and on 11/11/2022 was signed an Agreement with LLC Architects bureau "Oksa". The Technical work project was prepared and confirmed on 03/01/2023.

2. Supervision of the implementation of the Technical work project. Procurement of the technical project supervision service was finished and an Agreement with LLC Architects bureau "Oksa" was signed on 11/11/2022. The service of the supervision of the Technical work project will be provided during the entire period of execution of the Contract works.

3. The Contract work of the school building renovation. The contract was signed on 31/01/2023 with LLC “Antares”. A document authorizing construction has been received. The Contract work will be done according to the prepared Technical work project of the school building. The duration of the contract is no longer than 10 months. 100 percent of the building's dismantling work completed.

4. Technical supervision of the school building Contract works. The Agreement was signed on 31/01/2023 with Dmitrij Mykolayovych Luboichenko. The service implementation of the technical supervision is the entire period of execution of the contract works.

5. Installation of bomb shelter for school students. The contract was signed on 11/03/2023 with LLC „Art Bud Service“. The duration of the contract is no longer than 7 months.

6. Technical supervision of the installation of bomb shelter for school students Contract works. The Agreement was signed on 28/03/2023 with Dmitrij Mykolayovych Luboichenko. The service implementation of the technical supervision is the entire period of execution of the contract works.

7. 15/05/2023, a memorandum of understanding on additional funding was signed with the Taiwanese Representative Office in Lithuania, which will be used for environmental improvement and landscaping.

8. School environmental improvement and landscaping works. On 09/08/2023, an agreement was signed with LLC "Galaktika". The duration of work is not more than 3 months.

 

Thoughts of Ukrainian children who moved to Lithuania because of the war:

SCHOOL OF THE FUTURE IN UKRAINE: PREPARATION OF A TYPICAL TECHNICAL PROJECT

Project value: 500 000 Eur

Estimated duration of project implementation: 20 months.

The aim of the project: to prepare a typical technical project for the construction of schools in Ukraine with the cooperation of Lithuanian, Ukrainian and international architects.

CloseProject activities and status

1. On October 5-6, 2023, a creative workshop of Lithuanian and Ukrainian architects, teachers and the community is organized for the preparation of an architectural competition for the future school project.

2. November 2023 it is planned to announce an architectural competition for the preparation of a typical project of the Future School;

3. At the beginning of 2024, it is planned to select the best project idea, with the author of which a contract for the preparation of a typical technical project is concluded.

STRENGTHENING OF THE ADMINISTRATIVE CAPACITY OF THE AGENCY FOR THE RESTORATION AND INFRASTRUCTURE DEVELOPMENT OF UKRAINE

Project value: 300 000 Eur

Estimated duration of project implementation: 9 months.

The aim of the project: to strengthen the administrative capacity of the Ukrainian Recovery Agency in line with the European Commission's pillar-based methodology (Pillar assessment) requirements.

CloseProject activities and status

1. September 2023 launching the preparation of documents for the procurement process in line with best EU practices and training in their application.

2. In autumn 2023, the elimination of internal control inconsistencies (internal control) starts. Gap filling) in preparation for the non-compliance assessment (Gap filling assessment) according to the European Commission's Pillar-Based Methodology (Pillar assessment) requirements.